A $121.2 million project has created a train station in downtown Windsor Locks that will begin serving passengers Sunday, providing expanded connections to Bradley International Airport and supporting redevelopment efforts in the town center.
Gov. Ned Lamont and state Transportation Commissioner Garrett Eucalitto announced the opening Tuesday during a ribbon-cutting ceremony at the station, located at 231 Main St.
The new station replaces an existing stop south of downtown, relocating CTrail Hartford Line and Amtrak service closer to businesses, housing, Windsor Locks Town Hall and the public library.
The project includes expanded CTtransit bus service to the airport, including new weekend connections. Route 24 buses will travel between the station and the airport’s Terminal A in approximately 12 minutes, operating every 20 minutes on weekdays and every 40 minutes on weekends.
“We built this new station to correct the missing link in the redevelopment of downtown Windsor Locks, connecting residents to jobs and travelers to Bradley International Airport and beyond,” Lamont said.
The station will serve 31 trains on weekdays, 23 on Saturdays and 24 on Sundays. CTtransit routes 24, 96E and 905 Express also will stop there.
The station features a roughly 500-foot platform providing accessible level boarding, 160 parking spaces, electric vehicle chargers, bicycle racks and a dedicated bus pickup and drop-off area.
Passenger amenities include heated waiting areas, Wi-Fi, ticket vending machines, seating and electronic information displays.
The $121.2 million investment includes $46.1 million for station and roadway improvements and $75.1 million for railroad track and pedestrian bridge improvements. Approximately 85% of the funding comes from the state, with the remaining 15% from federal sources.
State officials said the investment is expected to encourage additional downtown development, building on projects such as the Montgomery Mill residential redevelopment and Trinity Financial’s planned transit-oriented development.
Eucalitto said the station is projected to handle 43,000 passenger trips annually by 2030.
The project also includes approximately 1,800 feet of Main Street reconstruction, improved sidewalks and a pedestrian bridge connecting a new multiuse trail to the Windsor Locks Canal Trail.
Rail improvements include track reconstruction, realignment and construction of a new bypass track, along with upgraded signaling and safety systems.
Although passenger service begins Sunday, railroad construction will continue, with the full project expected to be completed in the spring of 2028.