The developers of a stalled 199-unit mixed-use project along the Farmington River are asking the town for five more years to build it.
The Launch at Farmington LLC has asked the Town Plan and Zoning Commission to extend a March 2022 site plan approval for 199 apartments and about 54,000 square feet of commercial space at 1349 and 1371 Farmington Ave. and two adjacent lots on Route 4.
In an Oct. 19 letter, attorney Robin Messier Pearson of Glastonbury-based Alter, Pearson & Hope asked the commission to consider the request at its Oct. 26 meeting.
Construction on the project hasn’t started and the site plan approval would expire March 7, 2027.
State law allows the commission to extend an approval for five more years, up to a maximum of 10.
Pearson said the delay was caused by the pandemic and the deaths of the project’s two main backers, Abe Kaoud and Jeff Scott. Settling their estates and transferring property interests took up much of the five-year window, she wrote.
“These difficult and trying events precluded the initiation of construction,” the letter states.
Kaoud, who co-founded the Kaoud Rugs chain, died in June 2024 at 83. His sons, Maurice and Charles Kaoud, now manage The Launch.
The company is a successor to the original applicants, Kaoud Real Estate Development LLC and, in part, JRF Management LLC.
Ownership of the roughly 25-acre site has split since the approval. The Launch bought part of the land from JRF in 2023. In 2024, Superheroes Properties LLC paid $1.5 million for 1349 and 1365-1371 Farmington Ave. and a vacant lot at 8218 Farmington Ave., HBJ reported.
The plan calls for converting the former McCallum industrial building, between Farmington Avenue and the river, into residential and commercial space, alongside new apartment buildings. The developers would also extend the Farmington Canal Heritage Trail across state and town land, into the site and along the river to Farmington Avenue.
The town rezoned the site to its Midpoint Development District in December 2020 and approved a master plan and special permit. According to the letter, those approvals don’t expire. The Inland Wetlands Commission approved the project in November 2021, and that permit would be extended automatically if the site plan is.
The Midpoint district has drawn opposition before. In July, the commission rejected a master plan and zoning changes for the Enclave at the Farmington River. That 237-unit project was proposed on about 80 nearby acres by National Land Holdings LLC, an affiliate of Minnesota-based Crown Equities. Residents had raised concerns about traffic, flooding and wildlife.