Northeast Utilities and NStar caved into Massachusetts’ demands to buy power from Cape Wind, and all but secured the Bay State’s approval on Wednesday for their proposed $4.7 billion merger.
Hartford-based NU and Boston-based NStar have been at odds with Gov. Deval Patrick’s administration since they first sought regulatory approval from Massachusetts for their merger. The state Department of Energy Resources wanted the merged company to buy the other half of power from the offshore wind project Cape Wind – providing the funding needed for the project to go forward – but NU and NStar resisted, saying the Cape Wind electricity was too expensive and they could meet their renewable energy goals buying from land-based wind power.
But Patrick and Tom May – NStar chairman, president and chief executive officer – announced the merged company will enter into a 15-year contract to buy 129 megawatts of power from Cape Wind. This comes in addition to the company’s contracts for 109 megawatts of onshore wind to meet its renewable energy goals.
“We recognize that the climate change goals set forth by Governor Patrick’s Green Communities Act will require aggressive action and we think the best way to meet those requirements is through a diversified portfolio of renewable resources,” May said in the announcement. May will be the new CEO of Northeast Utilities once the companies merge.
Cape Wind was a pet project of Deval, but the offshore wind plan was stuck as the developer couldn’t secure another buyer after Massachusetts’ other major utility – National Grid – agreed to buy half of the power produced. With the NU deal in place, Cape Wind now has sold 77 percent of its power.
NStar and NU also announced on Wednesday a deal with Massachusetts Attorney General Martha Coakley to provide a $21 million rate credit to customers NStar Electric, NStar Gas and NU’s Western Massachusetts Electric Co. All distribution rates will be frozen in Massachusetts until 2016.
The Massachusetts Department of Public Utilities still needs to sign off on the deals and finalize the merger, but with the agreements in place with DOER and Coakley, there are no more major interveners against the merger going through in Massachusetts. All parties have requested an approval date of April 4 or earlier.
The Massachusetts DPU approval was considered to be the hardest approval for the companies to achieve, as the state was expected to impose a number of conditions regarding rates and renewable energy. With the Massachusetts approval, the two companies only need the go-ahead from the Connecticut Public Utilities Regulatory Authority to finalize the merger. PURA is expected to make a final decision April 2.
NU and NStar also agreed to honor all of their existing labor agreements; perform no broad-based employee layoffs; enter into long-term contracts for 10 megawatts of solar power; reduce electric use 2.5 percent annually beginning in 2013 by increasing energy efficiency measures; and put an electric vehicle pilot program in place in Massachusetts, mirroring similar work done by NU in Connecticut.
If approved, the merged company called Northeast Utilities will be the largest utility parent in New England with 3.5 million customers in Connecticut, Massachusetts and New Hampshire, spread out over six natural gas and electric subsidiaries, including Berlin-based Yankee Gas and Connecticut Light & Power.