New building proposed on vacant lot for Bristol manufacturer

A Bristol manufacturer is seeking city approval to build a nearly 68,000-square-foot facility on Clark Avenue, more than tripling the amount of space it currently occupies in the city.

Lee Spring, which has a 20,396-square-foot building at 245 Lake Ave., submitted the application on Oct. 15 for a new manufacturing facility at 681 Clark Ave.

The application, filed by Torrington-based Borghesi Building and Engineering on behalf of Lee Spring, is listed as the sole item under new applications received by the Bristol Planning Commission, which is scheduled to meet Monday at 6 p.m.

The proposed 68,008-square-foot building would be constructed on a 21.07-acre vacant property.

ADVERTISEMENT

According to the application, the property is divided between two zoning districts, an industrial park zone and a residential zone. All construction would occur within the industrially zoned portion of the site.

The application identifies attorney Stephen O. Allaire of Bristol as the property owner.

The site plans include a driveway providing access to the facility from Clark Avenue, as well as a second driveway for employees connecting to Matthews Street.

They also show space for a potential future addition of about 37,000 square feet, but that is not part of the current proposal.

ADVERTISEMENT

The property includes wetlands within the industrially zoned area, and the project requires approval from the city’s Inland Wetlands Agency. An application was submitted to that agency Sept. 25.

According to the project narrative, the site meets applicable drainage requirements, including a detention basin intended to improve adjacent wetland habitat.

The developer also states that the project meets zoning requirements for setbacks, lot coverage, buffers, landscaping and other site standards.

The application does not disclose the estimated construction cost, anticipated number of employees or a timetable for completing the project.