Enfield PZC OKs Winstanley distribution center

Despite scores of neighbors opposing it, Winstanley Enterprises’ massive distribution center planned for 35 Bacon Road in Enfield received unanimous approval Thursday from the Planning and Zoning Commission, although Chairman Lewis Fiore shared that it was one of the hardest decisions he’s made as an elected official.

“Over my years of service to this town — which have been many — I have had to make some difficult decisions,” he said at the PZC meeting held in Town Hall. “I can say with confidence this is one of the toughest decisions I have ever had to make.”

The one-story 819,000-square-foot warehouse/distribution center to be built on farmland between Crescent and Shaker Pines lakes, will have two tenant spaces — one occupying 318,000 square feet, the other 501,000 square feet. The project also includes parking, loading docks, and trailer parking at the rear of the existing Winstanley Logistics Center at 25 Bacon Road.

Members of Save The Lakes Enfield, a group of more than 400 residents who live in the area and oppose the center being built on Bacon Road, have spoken out against it during public hearings held before the PZC as well as the Inland Wetlands and Watercourses Agency.

ADVERTISEMENT

And even through the Inland Wetlands and Watercourses Agency approved a wetlands permit for the project last month before it moved on to the PZC, a handful of residents on Feb. 16 filed an appeal in Hartford Superior Court seeking reversal of that decision.

Concerns voiced by residents have included water runoff and the potential for flooding homes on the lakes and other areas of town; impact on traffic; road safety, and a likely increase in accidents that will further tax police and firefighters and endanger citizens; noise, light, air, and water pollution; considerable tree removal; displacement of wildlife; road degradation; and declining home values.

The group hired Steven Trinkaus, owner and principal of Trinkaus Engineering LLC of Southbury, to review Winstanley’s site plan. In Trinkaus’ report, he outlined his concerns about the project’s storm water management, which he said is not in compliance with requirements found in the state Department of Energy and Environmental Protection’s 2004 storm water quality manual.

Before the PZC vote on Thursday, members questioned Winstanley representatives about various aspects of the project concerning sound mitigation, entrances to the facility for the Fire Department’s emergency use, vegetation buffers, lighting, sidewalks on the property, soil contamination tests, maintenance for berms, and traffic islands.

ADVERTISEMENT

Before approving the site plan, the commission set more than 30 conditions including that Winstanley must install islands on entrances to 25 and 35 Bacon Road, submit a storm water management plan, refrain from using contaminants, and come up with a planting plan for the Cottage Road berm. Winstanley representatives agreed to the conditions.

PZC member Frank Alaimo said he lives in the North Maple Street area and approved Winstanley’s site plan for a distribution center, currently under construction, in that neighborhood when it came up for review before the PZC.

“We represent you but also the entire community and we need to follow our charge here,” he said to the residents who attended the meeting. “We have to stay within the statutes and within the laws.

Alaimo said it seems to him Winstanley is a very cooperative company and is willing to make changes.

ADVERTISEMENT

“The community can be sure the property will be well maintained and safe,” he said.

Just before the vote, Fiore said he knows the lake community that will be most affected by the project very well.

“I know that you take pride in your neighborhood and want what’s best for your family’s quality of life,” he said. “That was clearly evident throughout this process and I do truly appreciate that.”

What was before this commission was the applicants’ site plan review of a permitted use, he said.

“Unfortunately, by law, our hands are tied as to what can be considered and what we can factor into any decision,” he said.

With a site plan review, as long as the proposal complies with existing zoning regulations and is a proper use, the commission must approve it, Fiore said.

“Had this been a special use permit or a zoning change request, we would have had much more leeway regarding the requirements,” Fiore said. “If that were the case, my vote might have been very different. But unfortunately, my hands are tied by decisions made back in the mid ’70s when these parcels were zoned or re-zoned to Industrial use.”