East Hartford Mayor Connor Martin has moved to terminate a 27-year tax agreement for a planned $120 million apartment complex, declaring the long-stalled development “dead for now” after years of delays and mounting financial obstacles.
Martin said Tuesday he is terminating the tax-fixing agreement for Concourse Park, a proposed 402-unit, market-rate apartment development on roughly 25 acres off Silver Lane, a site previously occupied by Showcase Cinemas.
A formal notice was mailed to developers Avner Krohn and Brian Zelman on Saturday, he said.
The decision followed months of negotiations aimed at overcoming infrastructure and financing challenges that repeatedly delayed the project. The final obstacle involved a request for approximately $3 million in additional public funding to cover a payment and performance bond required by the Capital Region Development Authority (CRDA), Martin said.
The town already conveyed the property to Krohn and Zelman for $1 last year, approved a 27-year tax incentive and committed $10 million in public funding toward infrastructure improvements.
Martin said the developers wanted the town to increase that infrastructure commitment to approximately $13 million, a request he ultimately rejected.
The decision effectively ends the development in its current form, Martin said, although he remains hopeful of reaching an agreement with Krohn and Zelman to advance multifamily housing on the site. That could involve reducing the size of the development, identifying new funding sources or bringing in a new developer.
Martin said terminating the tax agreement approved by the Town Council in 2022 makes the 402-unit project financially infeasible. But the action is not meant to end potential cooperation with the developers, he said.
“Our letter was more a declaration of reality that this deal simply no longer works,” Martin said.
Zelman, reached Tuesday, expressed hope that the development is still possible.
“We continue to have productive discussions with the town,” Zelman said. “It has been a great partner and we hope to find a solution that will allow us to move forward.”
Tax agreement
The loss of the tax agreement represents a major financial setback for the development.
The agreement, approved by the Town Council in February 2022, would have required the developers to pay $2,100 annually in property taxes for each apartment, with that amount increasing by 2% each year of the 27-year term. At the time, officials estimated the tax bill without the incentive at approximately $5,500 per apartment.
For a fully completed 402-unit development, the initial tax payment under that formula would amount to approximately $844,000 annually, compared with roughly $2.2 million without the incentive, based on the original estimates.
The agreement was subsequently amended several times as construction deadlines slipped and the development plan evolved.
Former Mayor Mike Walsh had projected the development would generate approximately $30 million in property taxes over the life of the project, compared with about $3.4 million if the property remained undeveloped. A later estimate put the projected tax revenue at approximately $34 million.
Years of delays
The decision represents a significant setback for one of East Hartford’s most ambitious redevelopment efforts.
The town purchased the former Showcase Cinemas property in 2016 and spent approximately $6 million acquiring the site and demolishing the abandoned movie theater complex.
In 2021, East Hartford selected Krohn and Zelman to transform the property into a high-end residential community.
Town officials viewed the development as an important component of efforts to revitalize the aging Silver Lane commercial corridor, with hundreds of new residents expected to help support nearby businesses and attract additional investment.
Last year, Zelman estimated the project would cost about $120 million to develop. Krohn has repeatedly stressed his commitment to the project, noting he has spent “millions” of dollars on predevelopment work.
Plans called for 309 apartments in eight three-story buildings, followed by a four-story building containing another 93 units. Amenities would include a clubhouse, swimming pool, coworking space and dog-washing station.

But rising interest rates and construction costs, along with difficulties securing financing, repeatedly delayed construction.
The town initially required developers to build at least 360 apartments, but reduced that minimum to 300 in 2023 to help the project move forward.
After several extensions and revisions to the development agreement, Krohn and Zelman acquired the property from the town for $1 in June 2025, having demonstrated access to approximately $70 million in financing.
The developers were required to begin construction within one year of acquiring the property, but missed that June 2026 deadline.
Rather than immediately terminate the tax agreement, Martin granted a 90-day extension while town officials worked with the developers and CRDA to resolve outstanding issues.
Efforts to salvage the deal
Martin continued to push for a resolution through the summer and early fall, even as Town Council members became increasingly skeptical of the project.
At an Aug. 18 meeting, Martin told council members the administration was exploring ways to reallocate public funds to address infrastructure bids that had exceeded available funding, prevailing wage requirements and the performance bond.
By September, Martin had granted another one-month extension and was pursuing a revised financing framework.
According to Sept. 15 Town Council minutes, the mayor was prepared to use up to $3 million in state bonding allocated to town development projects to help cover costs associated with the state’s prevailing wage requirement. That turned out to be unnecessary after the town received a determination from state officials that most of the development would not be subject to those requirements, Martin said.
The proposed additional aid also tied the project’s tax incentive to completion of all planned apartments, rather than the previously required minimum of 300.
Council members, however, expressed growing frustration with the developers’ repeated missed deadlines and advocated stronger financial penalties, consideration of alternative developers and potentially scaling back the project.
Council Majority Leader Sebrina Wilson, at one meeting, called for the town to simultaneously engage backup developers, while Council Chair Richard Kehoe emphasized the need for firm deadlines and meaningful financial consequences.
Martin said Tuesday that public sentiment had also soured as residents watched years pass without construction beginning.
He said the town had been willing to make significant concessions to keep the project alive, but he could not justify committing additional taxpayer resources to expenses he believed were the developers’ responsibility.
Final sticking point
Martin said one significant obstacle was eventually resolved when the state Department of Labor determined that prevailing wage requirements would not apply across the entire development site.
That eliminated a potential source of additional construction costs.
The town and developers also discussed restructuring the project so that public infrastructure funding could be concentrated on the portion of the site planned for the 93-unit apartment building, potentially reducing infrastructure expenses.
But the requirement for a payment and performance bond remained unresolved.
Martin said CRDA required the bond as a condition of using public funds. The bond was estimated to cost as much as $3 million, an expense the developers hoped the town would cover, he said.
Martin said East Hartford had already offered substantial financial assistance, and the request for it to pay for a performance bond was too much to ask.
The town’s latest extension expired Oct. 9.
At an Oct. 6 Town Council meeting, Martin warned that the tax agreement would be terminated unless the developers agreed to proceed under the existing framework by that deadline.
The council also voted unanimously to authorize a legal services contract with Pullman & Comley, capped at $70,000, covering both Concourse Park and a separate Silver Lane Plaza redevelopment.
Meeting minutes indicate the town was preparing for possible litigation involving Concourse Park.
What next?
Although the tax agreement is being terminated, the town does not automatically regain ownership of the property.
Krohn and Zelman still control the approximately 25-acre site, and the development agreement does not provide for its automatic return to municipal ownership if the project fails.
Martin said deed restrictions limit the property’s use to market-rate apartments, while provisions of the development agreement give the town approval authority over additional or replacement developers.
That leaves several possible paths forward.
The existing developers could return with a revised proposal, bring in another development partner or sell all or part of the property to another developer, subject to the town’s approval.
Martin said he would be willing to consider dividing the site into smaller projects or reducing the scope of the development.
The town faces the possibility of litigation or a prolonged stalemate if the developers decline to cooperate, outcomes Martin hopes to avoid.
Martin stressed that the town remains committed to its yearslong redevelopment efforts and eager to work with developers and investors.
The town has worked aggressively to encourage redevelopment along Silver Lane, its riverfront and elsewhere. Martin said he expects to continue offering incentives for developments when the benefits justify the expense.
He said he believes the town went to extraordinary lengths to accommodate the Concourse Park developers but ultimately had to draw a line.
“We just, we can only do so much, and I have to remain fiscally responsible,” Martin said. “This is taxpayer money, even if it’s coming from the state.”