The U.S. Environmental Protection Agency is scheduled this week to begin removing contamination from the Solvents Recovery Service of New England Superfund site in Southington.
The site used to be an approved hazardous waste treatment and storage facility that disposed of industrial solvents from 1957 to 1967 in two unlined lagoons. Although the solvent disposal was discontinued, the site remained a source of contamination until 1991 because of spills and poor housekeeping.
The site has been on the EPA’s national priority list for contamination cleanup for 31 years.
The remediation work to be started this week includes using electric heaters to vaporize the solvents and then extract them using a vacuum system. The process will take six months to complete.
When the remediation is complete, the area will be capped, leading to the construction of a new segment of the Farmington Canal Heritage Trail.